It’s Moving Along!

Mechanical and electrical rough-ins are well underway. The body of the OR hoard system has been installed.  Sections of HVAC ducting and heating lines have had pressure tests completed with documentation to be distributed. The sprinkler contractor has their materials on-site and is starting installation next week.

In the photo on the right, patient rooms with windows line the right side of the hallway. Below, just some of a large amount of infrastructure will end up tucked above a suspended ceiling.